On Going Projects

Project / Sub-Project Direct Cost Municipality Status of Accomplishment (Physical) Status of Accomplishment (Expenditure) Year As of Status Province
Bongabong River Irrigation Project 28,934,000.00 Roxas 40.98% 29.20% CY 2017 Monday, December 31, 2018 Ongoing Oriental Mindoro
MAYABIG CIS 23,000.00 Baco CY 2019 Thursday, January 3, 2019 Ongoing Oriental Mindoro
MATUNGAO CIS 4,314.00 Socorro CY 2019 Thursday, January 3, 2019 Ongoing Oriental Mindoro
Caraniogan SIP 35,000.00 Narra CY 2019 Thursday, January 3, 2019 Ongoing Palawan
Bagtingon Small Reservoir Irrigation Project 3,000,000.00 38.84% 38.84% CY 2016 Monday, December 31, 2018 Ongoing Marinduque
Timburan SIP 25,000.00 Taytay CY 2019 Thursday, January 3, 2019 Ongoing Palawan
Talog SIP 32,000.00 Taytay CY 2019 Thursday, January 3, 2019 Ongoing Palawan
Libertad SIP 25,000.00 Taytay CY 2019 Thursday, January 3, 2019 Ongoing Palawan
Nali CIS 1,000.00 Quezon CY 2019 Thursday, January 3, 2019 Ongoing Palawan
Mag-Asawang Tubig RIS 50,000,000.00 Naujan 97.46% 86.92% CY 2017 Monday, December 31, 2018 Ongoing Oriental Mindoro